Nimbnet Fast Charging Station

Sundsvall

About this location

  • Situated 10 km north of central Sundsvall
  • Just 1.5 km from a safe exit off the E4 highway
  • Average daily traffic (ADT) of 801-1200 heavy vehicles along the E4 highway
  • Birsta area is a popular shopping district north of Sundsvall with high demand of retail and delivery

Close by

  • Birsta City (1.5 km) is Sweden’s largest shopping centre in northern Sweden that boasts over 4 million annual customers
Station supported by the Swedish Energy Agency
July 2022

Project Granted

  • The Swedish Energy Agency decided to finance the project to build a fast charging station.
August 2022

New Location Needed

  • We learned that our original site was not feasible and we must find a new location for our charging station.
November 2022

Chargers Ordered

  • Due to the escalating lead times and upcoming price increases, we ordered our chargers early to ensure we would have them on time.
June 2023

Chargers delivered

  • Our chargers were delivered to our warehouse, ready to be installed.
April 2024

Two Potential Sites

  • We notified the Swedish Energy Agency that we signed two sites of great potential and would be applying for a change of location soon.
May 2024

Grid Connection and Energy Agency Update

  • Sundsvall Elnät confirmed that there will be enough power for the station. The Swedish Energy Agency granted us a change of location.
June 2024

Construction Permit Granted

  • The construction permit was granted by Sundsvall Municipality. Production of concrete foundations began and pipes and cables were ordered.
July 2024

Construction Permit Appeal Received

  • We received a couple of appeals, one of which was from the Swedish Transport Administration. We have asked the Swedish Energy Agency for an extension of the project.
TBD

Completion Date

  • Project completion date will be based on the Swedish Energy Agency’s decision.

Nimbnet Station Sundsvall