Nimbnet Fast Charging Station

Nordmaling

About this location

  • Sits between the towns of Umeå (60 km) and Örnsköldsvik (54 km)
  • Just 800 metres from a safe exit off the E4 highway
  • Average daily traffic (ADT) of 401-800 heavy vehicles along the E4 highway
  • SCA Wood operates Rundvik’s sawmill, which is estimated to have 40,000 70-ton timber and wood trucks annually
  • Olofsfors AB, a well-known steel production company, is also nearby

Close by

Station supported by the Swedish Energy Agency
JulY 2022

Project Granted

  • The Swedish Energy Agency decided to finance the project to build a fast charging station.
AUGUST 2022

New Location Needed

  • We learned that our original site was not feasible and we must find a new location for our charging station.
NOVEMBER 2022

Chargers Ordered

  • Due to the escalating lead times and upcoming price increases, we ordered our chargers early to ensure we would have them on time.
MARCH 2023

Electricity Confirmed

  • Vattenfall confirmed that there will be enough power for the station and sent a quote for the connection.
APRIL 2023

New Location Secured!

  • After months of hard work to find a new location, we finally signed a land agreement with Nordmaling Municipality.
MAY 2023

Swedish Energy Agency Update

  • The Swedish Energy Agency granted us a change of location and an extension of the deadline.
JUNE 2023

Chargers Delivered

  • Our chargers were delivered to our warehouse, ready to be installed.
OCTOBER 2023

Construction Permit Granted

  • The construction permit was granted by Nordmaling Municipality.
    November 2023

    Transformer Station Agreement

    • Nimbnet entered into an agreement to purchase a new transformer station.
      December 2023

      Groundwork Begins

      • Nimbnet hired a land contractor and started clearing trees but had to pause over the winter.
        April 2024

        Property Formed

        • The land survey was completed and the new property was formed and registered in the Property Register.
          MaY 2024

          Land Purchase Contract

          • We entered into a purchase contract with Nordmaling Municipality.
          June 2024

          Construction Supplies

          • Production of concrete foundations for all equipment began. Pipes and cables were delivered.
          September 30 2024

          Charging Station Completed

          • The charging station is scheduled to be fully operational!

            Nimbnet Station Nordmaling