Nimbnet Fast Charging Station
Nordmaling
About this location
- Sits between the towns of Umeå (60 km) and Örnsköldsvik (54 km)
- Just 800 metres from a safe exit off the E4 highway
- Average daily traffic (ADT) of 401-800 heavy vehicles along the E4 highway
- SCA Wood operates Rundvik’s sawmill, which is estimated to have 40,000 70-ton timber and wood trucks annually
- Olofsfors AB, a well-known steel production company, is also nearby
Close by
- Roma Pizzeria (1.1 km) is within walking distance
- Rundviks Now and Then (1.1km) offers a small convenient store next to the pizzeria
- IFK Rundvik (750 m) has a nice running and skiing track
Station supported by the Swedish Energy Agency
JulY 2022
Project Granted
- The Swedish Energy Agency decided to finance the project to build a fast charging station.
AUGUST 2022
New Location Needed
- We learned that our original site was not feasible and we must find a new location for our charging station.
NOVEMBER 2022
Chargers Ordered
- Due to the escalating lead times and upcoming price increases, we ordered our chargers early to ensure we would have them on time.
MARCH 2023
Electricity Confirmed
- Vattenfall confirmed that there will be enough power for the station and sent a quote for the connection.
APRIL 2023
New Location Secured!
- After months of hard work to find a new location, we finally signed a land agreement with Nordmaling Municipality.
MAY 2023
Swedish Energy Agency Update
- The Swedish Energy Agency granted us a change of location and an extension of the deadline.
JUNE 2023
Chargers Delivered
- Our chargers were delivered to our warehouse, ready to be installed.
OCTOBER 2023
Construction Permit Granted
- The construction permit was granted by Nordmaling Municipality.
November 2023
Transformer Station Agreement
- Nimbnet entered into an agreement to purchase a new transformer station.
December 2023
Groundwork Begins
- Nimbnet hired a land contractor and started clearing trees but had to pause over the winter.
April 2024
Property Formed
- The land survey was completed and the new property was formed and registered in the Property Register.
MaY 2024
Land Purchase Contract
- We entered into a purchase contract with Nordmaling Municipality.
June 2024
Construction Supplies
- Production of concrete foundations for all equipment began. Pipes and cables were delivered.
September 30 2024
Charging Station Completed
- The charging station is scheduled to be fully operational!