Nimbnet Fast Charging Station
HÄRRYDa – Project Cancelled
About this location
- Situated 11 km out of central Gothenburg
- Just off the exit on Route 40 and 7 km from E4 highway
- Average daily traffic (ADT) of 1600+ heavy vehicles along route 40
Close by
- Göteborg Landvetter Airport (3 km away) is Sweden’s second-largest airport serving the Gothenburg region.
Station supported by the Swedish Energy Agency
July 2022
Project Granted
- The Swedish Energy Agency decided to finance the project to build a fast charging station.
August 2022
New Location Needed
- We learned that our original site was not feasible and we must find a new location for our charging station.
November 2022
Chargers Ordered
- Due to the escalating lead times and upcoming price increases, we ordered our chargers early to ensure we would have them on time.
June 2023
Chargers Delivered
- Our chargers were delivered to our warehouse, ready to be installed.
April 2024
New Location Found
- Finally, a letter of intent was signed between Nimbnet and a landowner for a plot in Härryda.
May 2024
Swedish Energy Agency Update
- The Energy Agency granted us a change of location.
June 2024
Grid Connection and Plans for Construction
- Härryda Energi confirmed that there will be enough power for the station and sent a quote for the connection. We applied for a construction permit.
July 2024
Project Cancelled
- Despite our hard efforts, the project must be cancelled due to the landowner backing out of our agreement.