Nimbnet Fast Charging Station

HÄRRYDa – Project Cancelled

About this location

  • Situated 11 km out of central Gothenburg
  • Just off the exit on Route 40 and 7 km from E4 highway
  • Average daily traffic (ADT) of 1600+ heavy vehicles along route 40

Close by

Station supported by the Swedish Energy Agency
July 2022

Project Granted

  • The Swedish Energy Agency decided to finance the project to build a fast charging station.
August 2022

New Location Needed

  • We learned that our original site was not feasible and we must find a new location for our charging station.
November 2022

Chargers Ordered

  • Due to the escalating lead times and upcoming price increases, we ordered our chargers early to ensure we would have them on time.
June 2023

Chargers Delivered

  • Our chargers were delivered to our warehouse, ready to be installed.
April 2024

New Location Found

  • Finally, a letter of intent was signed between Nimbnet and a landowner for a plot in Härryda.
May 2024

Swedish Energy Agency Update

  • The Energy Agency granted us a change of location.
June 2024

Grid Connection and Plans for Construction

  • Härryda Energi confirmed that there will be enough power for the station and sent a quote for the connection. We applied for a construction permit.
July 2024

Project Cancelled

  • Despite our hard efforts, the project must be cancelled due to the landowner backing out of our agreement.

Nimbnet Station Härryda